Mall of Istanbul, Torunlar Construction

In the third phase of the Mall of Istanbul (MOI) shopping mall, ABS Plus disposable formworks were preferred as a car park ramp. The heights varied from 25 cm to 65 cm. ABS Plus solution was used for landscape filling applications during the first and second phases of MOI before. Torunlar Construction preferred ABS solution one more time for its car park ramps due to its lightweight and cost-effectiveness. The pipes were cut starting at 25 cm slightly increased to 65 cm in order to construct the ramp. With only 10 cm covering concrete, a high load-bearing capacity structure was created for vehicle traffic in this area.

To see all pictures please click here